Home > Services > Complete Streets & Trail Design > Market Street Streetscape Project: Phase 2

Client

Borough of Lemoyne
510 Herman Avenue
Lemoyne, PA 17043

Project Completion Date

Summer 2013

Construction Cost

$1,138,000

Project Overview

The Borough of Lemoyne received funding through the PCTI program to complete Phase II of their streetscape master plan. The proposed improvements are targeted for Market Street and also include improvements to the school route along 7th Street to the south of Market Street.

The purpose of the project is to improve the overall aesthetics along Market Street and incorporate complete streets elements to improve accessibility and pedestrian access along the corridor. This is consistent with the Borough’s effort to revitalize the downtown area. TPD assisted the Borough design review committee through a conceptual plan refinement, cost estimates and preliminary and final design on the project.

TPD was responsible for evaluating the master plan improvements, including lighting, rain gardens, intersection bulb-outs, school zone implementation, bicycle accommodations and other elements such as benches, trees, trash receptacles and signing. Upon completion of the public involvement stage, TPD completed the design and permitting process for the project.

TPD was responsible for the overall contract management of the project, including coordination with the project subconsultants. TPD was also responsible for the preparation of Plans, Specifications and Estimate package and related environmental documentation. TPD also developed bidding and contract documents in accordance with PennDOT bidding specifications.

TPD’s responsibilities included the following tasks:

- Conceptual Plan Refinement

- Stakeholders Meetings

- Public Involvement

- Project Management

- Categorical Exclusion Evaluation Document

- Plans, Specifications and Estimates package (PS&E)

- Coordination with PennDOT, Borough and Local Officials, and Subconsultants

- Erosion and Sediment Pollution Control Plans

- Pavement Marking and Signing Plans

- Utility Coordination

- Drainage Design

- Construction Services

- Maintenance and Protection of Traffic Plans